Project Quote Estimator: Price a Job From Best, Likely and Worst-Case Hours

List your tasks with best, most likely and worst-case hours. You will see expected hours and uncertainty for each, and three quotes: at the expected hours and with a one and two deviation cushion.

Last reviewed

Task 1
h
h
h
Task 2
h
h
h
Task 3
h
h
h
$
$
%

The tasks shown are examples. Enter your own estimates in hours.

Quote at the expected hours

$3,552.00

44.3 hours; $3,882 with a one-deviation cushion, $4,212 with two

Three ways to price it
BasisHoursCostPrice
Expectedabout 50% chance of finishing within it44.3$2,960.00$3,552.00
Expected + 1 deviationabout 84% chance of finishing within it48.9$3,234.95$3,881.95
Expected + 2 deviationsabout 98% chance of finishing within it53.5$3,509.91$4,211.89
Each task
TaskExpected hoursDeviation
112.672.00
225.334.00
36.331.00

The percentages assume the tasks are independent and the total is roughly bell-shaped. They are a guide, not a guarantee. Large unknowns, such as changing requirements, belong in the pessimistic hours.

Why a single hour estimate is not enough

Quoting a fixed price means you carry the risk. If you guess one number of hours for a task, you are quietly assuming that nothing goes wrong, and when something does, the extra time comes out of your pay. Estimating three numbers per task, a best case, a most likely case and a worst case, shows how uncertain the work really is, and lets you price that uncertainty on purpose.

This calculator uses the three-point method from PERT, the Program Evaluation and Review Technique, which was developed for planning large projects. It turns each task’s three estimates into an expected number of hours and a measure of the spread, adds them up across the project, and prices the job at the expected hours or with a cushion.

The calculation

For each task, with O the best case, M the most likely case and P the worst case:

  • Expected hours = (O + 4 × M + P) ÷ 6.
  • Standard deviation = (P − O) ÷ 6, a measure of how uncertain the task is.

For the whole project:

  • Expected hours are the sum of the tasks’ expected hours.
  • Standard deviation = the square root of the sum of each task’s squared deviation. This treats the tasks as independent, so some of their surprises cancel out and the total is less uncertain than the tasks added together.
  • Labour = hours × your hourly rate. Cost = labour + other costs. Price = cost × (1 + margin).

The calculator prices three versions: the expected hours, the expected hours plus one standard deviation, and plus two. On a bell-shaped distribution these give roughly a 50%, 84% and 98% chance of finishing within the hours priced.

Worked example

Three tasks, with estimates in hours:

Task Best Likely Worst Expected Deviation
1 8 12 20 12.67 2.00
2 16 24 40 25.33 4.00
3 4 6 10 6.33 1.00
  • Task 1: (8 + 4 × 12 + 20) ÷ 6 = 12.67 hours, deviation (20 − 8) ÷ 6 = 2. The other tasks work the same way.
  • Total expected hours = 12.67 + 25.33 + 6.33 = 44.33.
  • Total deviation = √(2² + 4² + 1²) = √21 = 4.58 hours.

At a rate of 60 an hour, with 300 of other costs and a 20% margin:

  • Expected hours: labour 2,660.00, cost 2,960.00, price 3,552.00.
  • One deviation more (48.92 hours): cost 3,234.95, price 3,881.95.
  • Two deviations more (53.50 hours): cost 3,509.91, price 4,211.89.

Pricing at the expected hours means you will overrun about half the time. The cushion buys a much better chance of keeping the margin you quoted.

Points to check

  • Put real unknowns in the worst case. A task with unclear requirements needs a wide gap between best and worst.
  • Break big tasks down. Tasks of a few days each give better estimates than one task of several weeks.
  • Do not forget the work around the work. Meetings, revisions, testing and handover take time. Give them their own tasks.
  • Fixed price or hourly? For uncertain work, quoting a range or an hourly rate with a cap shifts some risk back to the client.
  • The margin is not profit. It covers unbilled time, tax and the months between jobs. The freelance hourly rate calculator shows how to set the rate.

Related tools: the freelance hourly rate calculator, the contractor versus employee comparison, the margin calculator and the standard deviation calculator.

Frequently asked questions

What is a three-point estimate?

It is an estimate made from three numbers for each task: a best case, a most likely case and a worst case. The PERT method weights them as best plus four times likely plus worst, divided by six, to give an expected duration that leans toward the likely case.

How is the uncertainty measured?

The standard deviation of a task is the worst case minus the best case, divided by six. For the project the squares of the tasks’ deviations are added and the square root taken, which assumes the tasks are independent, so the total is less uncertain than the tasks added together.

What do the one and two deviation quotes mean?

They add one or two standard deviations to the expected hours. On a bell-shaped distribution that gives roughly an 84% and a 98% chance of finishing within the hours priced. The figures are an approximation, not a promise.

Which quote should I give a client?

Pricing at the expected hours means a bad outcome comes out of your margin about half the time. Many freelancers price somewhere between the one-deviation figure and the expected one, and quote a range when the work is uncertain. The choice is yours.

What should the margin cover?

The margin is added on top of cost, which is your time at your rate plus other costs. It should cover unbilled time, tax and the gaps between jobs. Use the freelance hourly rate calculator to check that your rate already covers these.

Does this work for a team?

Yes, if you enter the total hours of everyone and use a blended hourly rate. The method adds hours across tasks regardless of who does them. If tasks depend on one another, the independence assumption fails, so use a larger cushion.