Concrete Calculator: Cubic Yards, Cubic Metres and Bags

Enter the size of your slab, footing, wall, column or post holes. You will see the concrete in cubic yards, cubic metres and cubic feet, how many bags of each size it takes, and the weight.

Last reviewed

ft
ft
in
%

Concrete to order

1.63 yd³

1.25 m³, including 10% allowance

80 lb bags needed
74
Volume, no allowance
40.00 ft³
Volume with allowance
44.00 ft³
Weight of the concrete
6,160 lb
Bags of each size
BagYield eachBags
40 lb (18.1 kg)0.3 ft³147
50 lb (22.6 kg)0.375 ft³118
60 lb (27.2 kg)0.45 ft³98
80 lb (36.2 kg)0.6 ft³74
90 lb (40.8 kg)0.675 ft³66

Yields are for QUIKRETE Concrete Mix; other brands differ, so check the bag. For a large pour, ready-mixed concrete is ordered by the cubic yard or cubic metre. Not engineering advice: structural work needs a design.

How the volume is worked out

The volume of concrete is the volume of the space you fill:

  • A slab, footing or wall is a box: length × width × thickness.
  • A round column or post hole is a cylinder: π × (diameter ÷ 2)² × depth.

Multiply by the number of identical pieces, and add an allowance for waste. The calculator then converts the result to cubic yards (the unit ready-mix is ordered in across the US), cubic metres and cubic feet. The conversions are exact: a foot is exactly 0.3048 m, an inch is exactly 25.4 mm, and a cubic yard is 27 cubic feet, which is 0.764555 cubic metres.

Work in one unit throughout. If your slab is 10 ft by 12 ft and 4 in thick, the thickness is 4 ÷ 12 of a foot, not 4.

Worked examples

A 10 ft × 12 ft slab, 4 in thick. The volume is 10 × 12 × (4 ÷ 12) = 40 cubic feet, which is 40 ÷ 27 = 1.481 cubic yards, or 1.133 cubic metres. With a 10% allowance it is 44 cubic feet, 1.630 cubic yards. In 80 lb bags, which yield about 0.60 cubic feet each, that is 44 ÷ 0.60 = 73.3, so 74 bags. The concrete weighs about 44 × 140 = 6,160 lb.

A 3 m × 4 m slab, 10 cm thick. The volume is 3 × 4 × 0.10 = 1.2 cubic metres, which is 42.38 cubic feet or 1.570 cubic yards. With 10% extra it is 1.32 cubic metres, or 1.726 cubic yards.

Six post holes, 12 in across and 36 in deep. Each is π × 0.5² × 3 = 2.356 cubic feet, so six take 14.14 cubic feet, or 15.55 cubic feet with 10% extra. That is 15.55 ÷ 0.60 = 25.9, or 26 bags of 80 lb.

A 10 ft × 12 ft slab at different thicknesses

Thickness Cubic feet Cubic yards Cubic yards with 10% 80 lb bags with 10%
3.5 in 35 1.296 1.426 65
4 in 40 1.481 1.630 74
5 in 50 1.852 2.037 92
6 in 60 2.222 2.444 110

Bags

The number of bags is the volume with allowance divided by the yield of one bag, rounded up. The yields are from the data sheet for QUIKRETE Concrete Mix:

Bag Yield
40 lb (18.1 kg) 0.30 cubic feet
50 lb (22.6 kg) 0.375 cubic feet
60 lb (27.2 kg) 0.45 cubic feet
80 lb (36.2 kg) 0.60 cubic feet
90 lb (40.8 kg) 0.675 cubic feet

Other makes of concrete mix yield a little more or less, so check the yield printed on your own bag. The data sheet gives the unit weight as about 140 pounds per cubic foot, which is where the weights come from.

The allowance

Concrete is lost to spillage, uneven sub-bases and forms that are not perfectly square, and it is better to have a little spare than to run short mid-pour, when the first batch is already setting. The calculator adds 10%, which is our default, not a rule. Change it for the job: a careful pour into tight forms may need less, and a rough excavation more.

What to watch

  • Minimum thickness. The QUIKRETE data sheet says the mix is for pouring 2 in (50 mm) thick or more. For a thinner layer you need a different product, and the calculator warns you.
  • Mixer capacity. The data sheet says to allow at least 1 cubic foot of mixer capacity for each 80 lb bag mixed at one time.
  • Large jobs. Above a few cubic yards, ready-mixed concrete delivered by truck is usual, and it is priced by the cubic yard or cubic metre, so the headline figure is the one to give the supplier.
  • Structural work. Footings, retaining walls and anything that carries a load need a proper design, reinforcement and local code. A volume is only the first step.

For other volumes and conversions see the volume calculator, the area calculator and the volume converter. The length converter and weight converter turn feet into metres and pounds into kilograms.

Frequently asked questions

How do I calculate how much concrete I need?

Multiply length × width × thickness, all in the same unit, to get the volume, then divide cubic feet by 27 for cubic yards. A slab 10 ft × 12 ft × 4 in is 10 × 12 × (4 ÷ 12) = 40 cubic feet, which is 1.48 cubic yards.

How many bags of concrete do I need?

Divide the volume in cubic feet by the yield of one bag and round up. A QUIKRETE 80 lb bag yields about 0.60 cubic feet, so 44 cubic feet (the 40 above, plus a 10% allowance) takes 44 ÷ 0.60 = 73.3, which is 74 bags.

How much does a bag yield?

For QUIKRETE Concrete Mix the data sheet gives about 0.30 cubic feet for a 40 lb bag, 0.375 for 50 lb, 0.45 for 60 lb, 0.60 for 80 lb and 0.675 for 90 lb. Other brands differ, so read the bag.

Should I order extra?

The calculator adds an allowance for waste, spillage and uneven ground, 10% unless you change it. That figure is our default, not a rule. Uneven sub-bases and over-dug footings take more than flat, square ones.

How many cubic metres is a cubic yard?

One cubic yard is 27 cubic feet, which is 0.764555 cubic metres, because a foot is exactly 0.3048 m. A cubic metre is 1.30795 cubic yards. A 3 m × 4 m slab 10 cm thick is 1.2 cubic metres, or 1.57 cubic yards.

How much does concrete weigh?

The QUIKRETE data sheet gives a unit weight of about 140 pounds per cubic foot (2,242.5 kg per cubic metre). So a cubic yard weighs about 3,780 lb, and the 44 cubic feet for the 10 ft × 12 ft slab weigh about 6,160 lb.